SPP-17 Lodgement Procedures

Version 1 – 13/03/2018

This guide is intended as general information only. If you are uncertain of your rights or interests, please seek professional legal advice. Landgate staff are not able to give legal advice or to draft your documents. Please read our Terms of Use above.

1     Manual Lodgement Procedure for Deposited Plans (replaces SPPM Chapter 17.1)

Manual lodgement of Deposited Plans is no longer acceptable. All Deposited Plans must now be lodged electronically. Appendix 6 (APX-06) provides guidelines on the preparation and lodgement of electronic plans.

2     Lot Synchronisation (replaces SPPM Chapter 17.2)

From 1 June 2010, after a successful trial period, Landgate has allowed the lodgement of Deposited Plans and Strata/Survey – Strata Plans using the Lot Synchronisation (Lot Sync) process.

Lot Sync reduces the processing time for the issue of new Certificates of Title.  This is achieved by using earlier lodgement of registration documents, parallel processing and different timing points when examining the Plan and examining the documents.  To provide an opportunity for all developers, Landgate is also including into the process Plans not requiring Western Australian Planning Commission (WAPC) endorsement.

Lot Sync has been initiated by Landgate as part of its commitment to improve the supply and availability of land to market.  It is intended to align Landgate with other agencies, utilities and stakeholders with regard to the registration of new lots.  Using the Lot Sync process to lodge a Plan ensures Certificates of Title will be issued as close as possible to the WAPC endorsement date for the plan of subdivision.

Lot Sync is voluntary and is intended as an alternative method for parties to lodge Plans and documents; it does not replace the current lodgement process.

Lot Sync is only applicable in cases where the documents are lodged before the plan is ‘In Order for Dealings’.

2.1 Lot Sync Business Process

When lodging Plans using Lot Sync, all registration documents (except for the production of the duplicate certificate of title) must be lodged within 10 working days after the Plan is lodged.  The duplicate certificate of title must be produced prior to the Plan being placed ‘In Order for Dealings’.

If there is any non-compliance with the rules the Plan will not be examined using Lot Sync and the documents will not be examined until the Plan is ‘In Order for Dealings’.

2.2 Lot Sync Rules
2.2.1 Lodgement of Plans
  • “Lot Sync” must be ticked on the NLR-P Lodge Plan Information screen

Lodge Plan Information

  • For Strata Plans, all relevant and available forms must also be submitted at Plan lodgement.
  • All required registration documents, including the Application for Title, to complete the issue of titles by the Registrar must be lodged at Landgate within 10 working days of the Plan lodgement.
  • A signed letter of acknowledgement for the document registration date must also be submitted by the lodging party. (See section 2.5 Change of Date Letter Template below.)
  • The normal lodgement fees for both Plans and registration documents will be applied.
  • Any Plan and registration document errors will be subject to the regulated requisition fees.
2.2.2 Lodgement of Registration Documents
2.3 Costs
2.4 Subdivisional Plan– Lot Sync Process

Subdivisional Plan - Lot Sync Process

2.5 Change of Date Letter Template

Landgate

Midland Square

Midland

I ……………………………………… am the (Solicitor/Settlement Agent) for the applicant. I have authority to make and to authorise on behalf of such persons the following amendment.

I acknowledge that the registration date for the documents necessary to issue Certificates of Title and any following documents for DP ………………….. will be altered to concur with the yet to be established ‘In Order for Dealings’ date of the said Deposited Plan.

_______________________________________

Signed

_______________________________________

Position

_________________________

Date

3     Electronic Lodgement of Deposited Plans (replaces SPPM Chapter 17.3)

ePlans prepared in accordance with the guidelines at Appendix 6 (APX-06) must be lodged in NLR-P.

4     Electronic Lodgement of Field books (replaces SPPM Chapter 17.4)

Surveyors must lodge field records at Landgate electronically in NLR-P in accordance with the guidelines at Appendix 6 (APX-06).

Surveyors are advised that Deposited Plans lodged with Landgate that require a field book will not be examined until the field book has also been lodged.  Plans without the necessary field book(s) will lose priority and be given a status of “Stopped”.

5     Two-year Certificate (replaces SPPM Chapter 17.5)

Where a Plan is not lodged within two years from the time of ground marking then a ‘Two Year Certificate’ is required (see regulation 53A of the Licensed Surveyors (General Surveying Practice) Regulations 1961) to certify that the survey has been inspected and that all marks have been verified.

The letter should be addressed to the Inspector of Plans and Surveys and accompany the Plan when it is lodged.

6 Countersigned Certificate (replaces SPPM Chapter 17.6)

Where a certifying surveyor is not eligible to verify Plans, the Plans must be countersigned by an ‘Eligible Surveyor’ before they can be lodged. The Certificate to be shown on the Plan is included at Plan Practices Section 12. See plan example 49.

7    Crown Survey/Drafting Contract (replaces SPPM Chapter 17.7)

The flowchart below (Figure 1) details the Crown Survey/Drafting contract process from the planning stage through the issue of the contract, lodgement, registration and the examination/validation process.

The survey/drafting contract is issued giving instructions as to the locality of, and the requirements for survey, as well as details for graphic presentation. Another form listing ‘Crown Drafting requirements’ and ‘Additional Notes’ is also provided with the instructions.

Surveyors are requested to notify the Central Issuing Office (Survey Coordination), Land Use Management, Department of Planning, Lands and Heritage, if they are unable to comply with the completion date shown on the Face Sheet.

A Plan Approval Requirements Sheet/Ministerial Order Sheet will be issued with each contract. This sheet will list consents required for the removal of constraints to Plan approval along with Ministerial Orders for the disposal of subject lands.

Any subsequent contact with Landgate, with regard to further direction for the survey or preparation of the graphic, should be the subject of the surveyor’s report, detailed on the Survey/Drafting Instructions.

Surveyors should address any land management issues affecting the survey and consult with Central Issuing Office (Survey Coordination), Land Use Management, Department of Planning, Lands and Heritage, if necessary.

Regional Manager

Responsible for land management issues, application approvals and survey recommendations

  1. CENTRAL ISSUING OFFICE (CIO) - Survey Co-ordinator

    1.         Ascertains client and Departmental requirements

    2.         Researches survey requirements

    3.         Lists graphic requirements

    4.         Generic lot number 0 range allocated

    5.         Ascertains legal constraints to plan approval

    6.         Issues Survey/Drafting contract

    7.         Updates PROMPT

  2. SURVEY FIRM (CONTRACTOR)

    1.         Effects survey and liaises to resolve any anomalies

    (including land management issues)

    2.         Organises drafting whether “in house” or to private drafting firm

    3.         Surveyor validates survey, graphic and digital data

    4.         Surveyor signs certificate(s) on plan

    5.         Field book, plan, digital data, survey report form, Surveyor’s self-assessment                   lodgement form, survey information and account lodged with CIO, DPLH. Electronic             field books (EFB) to be lodged directly with Landgate. See Appendix 6.

  3. CENTRAL ISSUING OFFICE (CIO) - Survey Co-ordinator

    1.  Ensures information received satisfies contract requirements

    2.         Submits field book to Landgate for lodgement

    3.         Validates and authorizes payment of account

    4.         Updates PROMPT

    5.         Pay lodgement fees

    6.         Sends copy of lodgement receipt and clearances to WAPC.

    7.         Forwards case for processing

  4. LANDGATE

1.         Authorises Plan lodgement and registration

2.         Examinations plan

3.         Validates Certification Requirements Sheet

4.         Requisition for errors (where necessary – plan stopped)

5.         Drafting amendments by contractor (when necessary)

6.         Plan certified ‘In order for dealings’

Figure 1: Crown Survey/Drafting Contract Process

8 Search Information (replaces SPPM Chapter 17.8)

A complete search for a Crown survey/drafting contract shall include the following:

  • Extract from Spatial Viewer and print of Public Plan if necessary;
  • All Survey Index Plans (including imperial Key Sheets if applicable);
  • All survey plans (including their Title Blocks) and relevant titles;
  • Field notes, and
  • Any other relevant data and its source e.g. Geographic Names.

Upon lodgement, the survey information must comprise a clearly indexed copy of the SIP along with sequential copies of Plans and field notes. This search is essential for the examination/validation process and poor quality information may be subject to a requisition. Survey information will be returned if requested.

9 Lodgement of Crown Plans (replaces SPPM Chapter 17.9)

On completion of a Crown survey/drafting contract, the surveyor (or agent) presents the following to the Survey Coordinator, CIO, State Land Services.

  • Field book (Electronic Field Books lodged directly with Landgate).
  • Survey Plan (ePlan for lodging at Landgate).
  • Digital Data - separate file for each Plan with the file name noted in pencil on the Plan, in CSD format on a CD-ROM.
  • Full search information.
  • Account or copy of account (as applicable).

The Survey Co-ordinator:

  • Assesses the returned information for compliance with contractual requirements
  • Verifies surveyor’s certification of the Plan and field book and Eligible Licensed Surveyor certification, if applicable.
  • Lodges the field book with Landgate.
  • Obtains CIO file.
  • Authorises payment of account.
  • Forwards the contract ‘case’ to Landgate for Plan lodgement and examination/validation. Pays plan lodgement fee.